top of page

Florida HOA Architectural Approvals: The Building Permit Mistakes Boards Must Avoid

Writer: José R. Hernández
José R. Hernández
10 minutes ago
6 min read

A homeowner submits a complete application for a new screened lanai. The plans are attached, the materials are listed, and the contractor is ready. The architectural committee sends it back with a short note: "We will not review this until you provide an approved county building permit."


For years, many Florida associations treated that response as standard practice. As of July 1, 2026, it is no longer allowed. A recent change to Florida Statute 720.3035 prohibits HOAs and their architectural committees from requiring an issued government building permit before reviewing an improvement application.


If your board's forms, guidelines, or habits still include this requirement, now is the time to update them. This article covers what the law changed, what your committee can still require, how to document approvals and denials, and why HOA approval and building permits remain two separate steps.



HOA architectural application for a screened Florida lanai, showing a crossed-out red “Permit Required First” stamp beside a green “Ready for HOA Review” stamp, illustrating Florida’s 2026 building permit rule change.

What Changed Under Section 720.3035(1)(c)


The new provision is short and direct. An association, or any architectural, construction improvement, or similar committee, may not require a parcel owner to obtain a government-issued building permit as a condition for reviewing plans to build structures or improvements on the parcel.


In practical terms, your committee must accept and review a complete application even if the homeowner has not applied for a permit or received one yet.


Why the Legislature Stepped In


The old practice often created a frustrating loop. Some local permitting offices expect proof of HOA approval before they issue a permit. When the HOA also demanded the permit first, homeowners got stuck between two offices, each waiting on the other. Projects stalled, contractors moved on, and frustrated owners took their complaints to the board.


The law removes the requirement to obtain an issued building permit before HOA review, allowing homeowners to pursue architectural approval and government permitting without that prerequisite.


What This Means If Your Board Still Requires a Permit


Start by reviewing every document your committee uses. Look at application forms, published architectural guidelines, committee procedures, website instructions, and any template letters your manager sends. Remove any language that makes an issued permit a requirement for review.


Next, check pending applications. If your committee has set aside an application only because a permit was missing, move it into active review. Let the homeowner know in writing that the application is being processed.


Finally, brief your committee members and your management team. The most common compliance problems come from habit, not policy. One volunteer repeating "get your permit first" over the phone can undo a well-written policy.


What Architectural Committees Can Legitimately Require


The law does not take away your committee's ability to review projects carefully. It narrows one specific requirement. Your committee can still ask for the information it needs to judge whether a project meets community standards.


Authority Must Come From Your Governing Documents


Under Section 720.3035, your review authority extends only as far as the declaration of covenants or published guidelines authorized by the declaration. That authority must be specifically stated or reasonably inferred as to an improvement's location, size, type, or appearance.


In other words, your committee's requirements should tie back to your documents. If the declaration gives you authority over fence height and materials, you can ask for fence height and materials. If it says nothing about a topic, be cautious before creating a new requirement.


Information Committees Commonly Request


Depending on what your governing documents authorize, committees typically ask for:


  • Site plans or surveys showing the improvement's location on the lot

  • Drawings or specifications showing size, height, and design

  • Material types, colors, and finishes, often with samples or product sheets

  • Contractor information and the expected project timeline


These requests help your committee evaluate appearance and placement, which is the core of architectural review.


Limits Boards Should Know


The statute sets several other boundaries. Committees generally cannot regulate interior features that are not visible from the frontage, an adjacent parcel, an adjacent common area, or a community golf course. If your guidelines offer approved options for materials, design, or location, you cannot restrict an owner from choosing among those options.

Hurricane protection carries its own rules. Boards must adopt hurricane protection specifications and may not deny an application that conforms to them.


Whatever you require, apply it reasonably and equally to every owner. Consistency protects the board and supports community harmony.


How to Document Approvals and Denials


Good documentation does more than satisfy the law. It gives homeowners clear answers and gives future boards a reliable record.


Denials Must Be Specific and in Writing


Section 720.3035 requires a written notice for every denial. That notice must state with specificity:


  1. The rule or covenant the committee relied on

  2. The specific part of the proposed improvement that does not conform


A letter saying "your application does not meet community standards" falls short. A compliant denial might read: "Section 7.3 of the Architectural Guidelines limits rear-yard fences to 6 feet in height. Your proposed fence is 8 feet tall along the rear property line."

That level of detail helps the homeowner fix the problem and resubmit. It also shows the decision was based on written standards, not personal preference.


Approvals Deserve the Same Care


Approval letters should identify the project, the plans reviewed, and any conditions attached. If you approve a project with changes, such as a different paint color, put those changes in writing.


Keep a copy of the application, the plans, committee notes, and the final decision in the association's records. Organized files make it easier to answer questions later and help show that standards were applied evenly.


Why Specificity Matters Financially


The stakes are real. If an association or committee unreasonably, knowingly, and willfully infringes on an owner's rights under the declaration or published guidelines, the homeowner may recover damages, costs, and reasonable attorney fees. The statute also bars associations from relying on policies that conflict with the declaration, even if those policies were applied uniformly.


Clear, documented decisions are your best defense against disputes that drain association funds.


HOA Approval and Building Permits Remain Separate Requirements


Some homeowners may read the new law as "the HOA no longer cares about permits." That is not what it says. HOA approval and government permits are two independent requirements, and one never replaces the other.


HOA Approval Covers Community Standards


Your committee reviews whether a project fits the community's architectural standards. That usually means appearance, location, size, materials, and consistency with the neighborhood. These standards protect property values and the look of the community.


Building Permits Cover Code and Safety


Your county or city reviews whether a project meets building codes, zoning rules, and safety requirements. The HOA does not enforce the building code, and the permitting office does not enforce your covenants.


Neither One Replaces the Other


An HOA approval letter does not authorize construction without a required permit. A county permit does not override your covenants or architectural guidelines. Homeowners generally need both before work begins.


Help owners understand this from the start. Add a plain-language note to your application or approval letter explaining that HOA approval addresses community standards only, and that the owner remains responsible for any permits the local government requires. If your board wants to condition approval on obtaining permits before construction starts, review that language with your association's attorney so it does not function as a pre-review requirement.


Update Your Process Before It Becomes a Dispute


The 2026 change to Florida Statute 720.3035 is a small adjustment with real consequences. Boards that still require a permit before review risk delays, frustrated homeowners, and potential legal exposure.


The fix is straightforward. Review your forms and guidelines, remove any permit-first requirements, tie your committee's requests to your governing documents, and put every denial in writing with specific reasons. Then explain clearly to homeowners that HOA approval and building permits are separate steps.


A fair, well-documented approval process protects your community's future, reduces disputes, and shows homeowners that your board operates with transparency.

Disclaimer: This article provides general information only and is not legal advice. Consult a qualified Florida attorney about your association's governing documents and specific circumstances.


Did I miss anything? Please let me know in the comments! Also, please subscribe to our blog to receive notifications when new articles are published.



At Don Asher Management, we've proudly served the Central Florida community for over 70 years. As a locally owned company with a strong understanding of the local market, we've cultivated strong relationships with regional and national contractors to deliver top-quality services. We're dedicated to meeting your property and HOA management needs with a personalized touch, combining our decades of experience and commitment to detail to provide unmatched service. We're confident in our ability to deliver exceptional services tailored just for you. Choose Don Asher Management—where personalized attention meets professional service.

Comments


IREM.png
top_main_menu_1-e1522425355748.png
narpm-e1522425263242.png
communitylogo.png
realtor_logo-e1522425594271.png
Floridarealtors.png
orlandoregionalrealtor.png

©2019 by Don Asher and Associates, Inc. - 1801 Cook Ave. Orlando, FL  32806 - (407) 425-4561

bottom of page